Terebro supply specialist equipment for pipeline installation, diamond drilling and Tracked Utility Vehicles for all terrain access
Bohrtec BM150DT auger boring rig

BM150DT

House Connections From Inside A Sewer ID 1200 mm

The BM 150 DT is a powerful machine for constructing small diameter house connections from walk in Sewer DN 1200 and bigger Due to the fact that the machine can be installed in the Sewer very accurately, there is no need for an expensive guidance system.

Method Of Operation

  1. After installation of machine and power pack in the collector a core drill unit is used to prepare the start position.
  2. With the drilling head in the first steel jacking pipe the further pipes are injected one by one until the head reaches its target.
  3. The head is then unscrewed and replaced with a pulling adapter. Using a specially designed pulling unit the product pipes are pulled in one by one.
  4. With each product pipe pulled in, a steel jacking pipe is ejected into the collector where it is stored for the next connection thus saving set-up time.
  5. When the product pipes reach the collector, the connection is completed using a link articulated seal.

Features

  1. Accurate drives up to 25 m
  2. Short set-up time
  3. Easy to use
  4. Competitive - even when compared with open cut
  5. Can be operated from Ø 1200 collector
  6. Core-drilling possible
  7. 24 kW electrical power-pack
  8. No guidance-system necessary
BM 150 DT TECHNICAL DATA
Jacking force 156 kN
Force on retract 93 kN
Torque 4000 Nm
Speed:
Core drilling
Auger
 
up to 130 rpm
70 rpm
Hydraulic pressure up to 250 bar
Stroke 2 x 430 mm
Weight 600 kg
Dimensions (l/w) 1.20mm / 0.90mm
Sewer ID 1200 mm or larger
Target hole 800 mm
Drive length up to 25 m
Max. pipe Ø (OD) 279 mm
Pipe Ø (OD) 219 mm
279 mm

Back to top

Site Navigation

News Section

Terebro Move Premises

Terebro Move Premises

In order to cope with our ever expanding fleet of guided augerbore equipment and to house our newly formed Safety Solutions department, Terebro have moved 2 miles down the road from Foxhill...
Read more...

Case Studies

Auger Boring – Why It's Big In Berlin

Auger Boring – Why It's Big In Berlin

Trenchless pipeline installation and rehabilitation is, in one sense, the Water Industry's equivalent of 'stealth' technology. When compared with open cut, it is very unobtrusive, often operating...
Read more...